As many times we explained before, our customer doesn't have forecast for this item and even they don't know product is continued in future or not. That mean they can ONLY know when their customer orders to them, and we can ONLY know when we receive order from our customer.
We deeply know that this requires long lead time, BUT we can't issue FC to you without information from our customer. What should we do if we issue FC to you, you prepare raw materials then our customer has no more PO? If you say we must do nothing, we will issue FC to you immediately. In fact, we must buy that raw materials, right? That's why we can't issue any FC to you recently.
Please kindly understand and so sorry for any inconvenience which may cause to you.