In the rolling horizon, inevery period, the data for the just completed period are replaced with new data from the period at the end of the new planning horizon. So if the planning horizon is
five periods, after the first period, the data for Period 1 are dropped, data for Period 6 are added and the multiperiod plan is recalculated. At the end of Period 2, the data for Period 2 are dropped and the data for Period 7 are added. The process continues every period
In the rolling horizon, inevery period, the data for the just completed period are replaced with new data from the period at the end of the new planning horizon. So if the planning horizon isfive periods, after the first period, the data for Period 1 are dropped, data for Period 6 are added and the multiperiod plan is recalculated. At the end of Period 2, the data for Period 2 are dropped and the data for Period 7 are added. The process continues every period