Your summary is alright. Please consider to my questions:
• When you found Scaffolding did not install in accordance to the standard, What and how did you advise the team?
• Long term FE scaffolding installation (more than 1 year) What did you suggest them to do?
• As you said “Writing scafftag incorrect of inspector” What does it mean exactly? What did you recommend them?.
• Used scaffold pipe to install tempo ladder instead of using standard ladder, What was your suggestion to them?
• Did you consult AI Supv on any deficient findings to solve the problem by discuss directly to the users or concerned people?