Dear Khun Burin,
As detailed to you in my email from 16/11, I clearly stated that we will pay the mentioned invoices in Mid December.
Florian along with Stefan have strongly pushed the Symbior Group and Investors to make an exceptional good faith payment before that Mid December, this is why we’ve prepared a payment for MS 13 for a total of THB 49,307,625, as you know we’ve deducted THB 2.6M for works on galvanisation. Please let us know
The other MS will be paid in Mid December according to the orignal schedule for warded on 11/16.
Also for your information we’ve been instructed that MS 6 has been removed from the payment list for Mid December because the dyke not complete.
Let me know if you have any questions.
Best regards,