Toilet Finishing. (Office)
Install Scaffolding Roofing Work.
Casting Wall Dock Leverler, Lean Drop Panel, Rebar Toilet 2.
Erection Truss Work.
Erection Truss Work.
Spk Setting Toilet 2, Street Light Set up.
Process Tusument Shop Drawing Work.
Safety Patrol Document.
Document & Gutter Work. (Casting Concrete)
Document & Gutter Work. (Casting Concrete)
Line Level Gutter.
Line level Lean Office.
Lean Slab & Rebar Slab Oil Tank.
Shop Conpany Pole.