There is one payment term for Lampsite & Civil Work Survey and Design:
One payment
Contractor shall issue Design Acceptance Certificate (DAC) to Subcontractor after Design Acceptance Test was finished then Subcontractor can invoice one hundred percent (100%) of total amount in Purchase Order. Payment will be made within 30 days by T/T or cheque after receipt of the following payment documents and on verification by Contractor:
A. Original Purchase Order
B. Original invoices
C. Design Acceptance Certificate (DAC) that issued by Contractor.