Minutes of meeting (9/10/2015) with MECT, Project Asia & Central group on the progress and plan ahead for Guestrooms.
Please find the following minutes of meeting:
1) Send shop dwg. of CP. (Pending conclusion from K.Poramate MECT)
- Standard of Lutron.
- Comment of the project.
2) Send the position of each CP for room type. (Pending conclusion from K.Poramate MECT)
3) Face plate of the CP is black stainless.
4) Face plate Termostat black colour.
5) The digital room thermostat not delivery to project.
6) The tem sensor has not delivery to project.
7) Mock up room equipment of Lutron in the room to be old. Sent new equipment for BOQ.
8) Transmission wiring diagram and load schedule for mock up room. (MECT informed the I-Style not installation terminal for the cable power supply for curtain and A/C.
9) K.Pornchai advise equipment I-Style already order to Lutron but Lutron not delivery to project.