Training:
After installation is completed, the supplier must train a minimum of 6 employees in the safe
operation of all pieces of equipment.
• Class room training: Need training in classroom 1 course / 6 person
• Onsite training: Need training on site minimum one week AFTER installation & commissioning
complete, 6 persons.
Schedule:
The quotation shall include a schedule in a Gantt chart form (or similar) format of the project.
Items to be included are:
Basic layout confirmed
PO awarded
Engineering & design including supply of drawings in AutoCad format.
Electrical Design Reviews (Accessories locations included)
Mechanical Design Reviews
Equipment Build plan
Acceptance @ Supplier date
Shipment date
Installation in Electrolux Thailand Rayong plant date
Commissioning date
Final Acceptance Run @ EHP Thailand Rayong plant.
Training (minimum 1 x week)
Start of Production.
Delivery & Timing:
Delivery estimation to be early to mid year 2015
Installation:
Unloading, unpacking and Installation of all 3 injection moulding machines is required and to be
included in the quotation. IF not included then please clearly advise?
All Cranes and equipment required is of the responsibility and liability of the supplier.
Payment terms:
Payment terms are specified in the Electrolux Purchase Agreement with detailed specific payment
percentages and intervals based on each schedule milestone.
Warranty:
Two yearswarranty on all structural, mechanical and electrical components.
Inspection:
Acceptance testing will be carried out in the manufacturer’s premises prior to shipment of any
equipment or presses. All specifications must be met before “acceptance” is granted.