According to date 3-4 Dember 2016, we had installed LOP+Indicator work for catch up the schedule for EVS inspection on 6 December 2016.
Result;
P3-4 install LOP with Indicator at permanent position have done already.
FL1 install indicator G-16th floor have done already, but LOP had installed G-5th floor only, cause of punching concrete work still not complete.