Hi All,
please refer to below summary for your action:
Management meeting & paperwork
- targeted submission for top view floor plan layout is still by this Friday [ current status: not started yet]
- targeted work plan presentation to FC's PM (Wai Bee) this Thu at 10 am IBM
- we did not set up targeted weekly meeting with user yet (all PMs should propose your time slot back to my attention before we meet Wai Bee this Thursday)
- it takes up to 2 weeks for user's approval to work at areas under their cares so please plan accordingly in advance
Schedule:
- Please refer to the excel attached. Work should start from 14 Nov onward. For IBM, cable must be ready by mid of next month for their new equipment commissioning. The other sites, target remains the same in end of Feb.
- System downtime on the excel is based on our request and it could be disagreed by users but this is the draft version and please be aware that only on Sunday that we can perform rack arrangement and it has only 12 Sundays for 20+ racks to handle for 4 different sites.
Dress Code:
- Lantro long-sleeve shirt: targeted delivery Totday current status not available yet but the next commitment is set on this Friday (50 items)
- Smock dress code : dress in BLUE
- Production Cap in GREEN net
- Safety Helmet is in YELLOW
- Safety vest is in BRIGHT YELLOW/ORANGE
Training
- Please fill in personal detail of each person and change company name to Lantro with running number with Full Face Photo and bring it on training day. Once the safety officer signed, then this card is valid 1 year.
- The Safety officer will random check for alcohol and drug consumption every day please take note on this and inform your team members.
Material
- targeted delivery (partially) and site preparation: on this Friday
- for fibre RYT has (SM outdoor) 2000,2000, 500, 200, 100 & 54 m. in stock please mobilise the loose cables right to the length perfectly. the rest is expected to deliver around 12 Dec.
- Boomlift => please confirm your schedule (available 2 months x 2 trips for Samrong, 1.5 months x 2 trips for TTN)
- Conduit => please confirm your BOM