As per discussed with worley parson on 12 Feb 2015 last.
As far as I understand, I try to list our requirement for PTTEP’s online sand monitoring project as information below krub.
1.) ( Hazardous area )
1.1 Sensor to install test header area have to possess appropriate elbow position.
1.2 Need to have adequate space for wiring RS-485 cable to interconnecting with Worley's Junction box, Ex e
1.3 Both WPS1 and WPS2 platform have to possess 24 Volt DC to be power supply to sensor.
1.4 Check port for RS-232 available in PTT's telecom equipment that supports each other?
1.5 Check radio links equipment to be transmitter whole slot, port, address destination with PTTEP system whether support or not?
Scaffolding description, I have to annoy both P'Kan and P'Peera that appropriate position for creating scaffold to wiring due to I don't have knowledge yet.
2.) (BCPP)
Major would be sand server have to possess specification who can interconnect to PI system for pull production data each wells come calculate
and pass data go to terminal who be sand client.