Please be note that both Project concern shutdown period as your proposed master plane to fabrication activities attached.
Still today not yet finished
Most of your planed activities delay. With schedule below
1.Why materials not arrived as your agreement schedule? Lack of good team procurement or project engineer didn’t schedule ?
2.Why problems with belzona coating training postpone 2 time first time since 26-27 Feb-15, second time 3-4 March-15, and next ? we think your master planed no meaning and can’t believe it. How to do? Most of your verbal confirmed and promised try to shipment with supply boat schedule on 7-March-2015, But failed of both project , how to do with your poor management and performance?