(h) In all cases where the Supplier has given notice under Sub-Clause 8.4 (Extension of Time for Completion), the Supplier shall consult with the Owner to determine the steps (if any) which can be taken to overcome or minimise the actual or anticipated delay. Without limitation, the Supplier shall take all reasonable steps to minimise delay to any Time for Completion, and shall comply with all reasonable instructions of the Owner in order to overcome or minimise such delay.