Regarding November supply of Ultra-S 4, we regret to inform you that we have to delay the shipments to load in end November – early December due to extremely tight production situation.
As so, we will not be able to supply any Ultra-S 4 more than 57 MT (3 Iso-tank) in November. This message about volume limitation in November is delivered commonly to all of our Ultra-S 4 customers.
We are exerting every effort to mitigate the impact of the supply reduction until the completion of turnaround and, at the same time, we would like you to cooperate to tackle this tight supply situation.
Once the production restarts on 27th November with the completion of turnaround, we will arrange the shipment for PSP as soon as possible.