Dear Khun Preecha,
1) I have corrected the safety manual as commented by TNC. Please resubmit for approval again.
2) For Building A comments by TNC last week, could you help to amend the site planning and resubmit again?
a. Removable opaque stickers instead of future board
b. Traffic speed limit – labour lead the vehicle during day time
c. Frequent transporting and loading & unloading of materials during night time after 11:00pm
d. TNC can allow like daily trip not more than 10 times
e. Traffic in/out by designated route and entrance – please get the road map from TNC for reference
f. Building A Stage 2 – show how people on wheel chair access to Chefman
g. Building A Stage 2 – ground floor access option B - recheck again for worker to go to toilet only, so see whether we can avoid extensive covered walkway
h. Any other comments by TNC?