As an option, Intamin can supply an initial spare parts package valued at EURO
50’000.00.
SUPER GYRO TOWER 1200 /110M - 9 –
A detailed spare parts list for the electrical and mechanical equipment used on the ride will be provided at least 3 months before the rides public operation based on discussions on the level of spares actually required.
By this it is ensured that the Buyer can order the needed spare parts in time so that they arrive together with the ride at the site. If recommended spare parts are not ordered or not made available by the Buyer during commissioning of the ride, any delay due the non-availability of such parts and all related consequences is the Buyer’s responsibility.
Intamin's rides are designed not only to minimise the cost of maintenance, but also by the use of commercially available components from leading suppliers. By this and wherever possible, the buyer can generally source many parts from local suppliers. Parts which are to be replaced during commissioning may be taken from Buyer’s stocks and replaced free of charge by the Supplier.
1 1 . A d v i s o r y S e r v i c e - O P T I O N
Optionally, Intamin can offer a package of 125 man-days for advisory service, both for installation and for the ride testing and commissioning as well as training of the operation-staff during the erection and testing schedule, as long as the staff to be trained does have sufficient theoretical knowledge, extended work experience in similar fields and speaks fluently English. The number of man-days for training amounts up to 5 and is included in the above mentioned total number of 125 man-days. The cost for this option is shown under Chapter E, Options.
The package of man-days is considered sufficient for this type of ride, conditional to an uninterrupted work progress, no delays due to other work carried out along the ride and the installation team (mechanics/electricians), provided by the Buyer, is of a sufficient number, English speaking, knowledgeable and properly equipped.
Site Acceptance Test Plans will be submitted for review and approval. The suggested package of man-days includes testing of the safety devices, critical components and monitoring elements onsite.
The goods are fabricated according to the Factory Quality Management Plans but no tests of subassemblies at the factory are included.
The Buyer is responsible to grant access to transports, heavy equipments (cranes) and suppliers personnel. The Buyer will also make all necessary preparations of the construction site, like fencing, suitable lay-down area adjacent to the installation site (to