From Inquiry with K.Payao (Account Senior Specialist) ; found that the Company have only a savings account. The nature of the settlement are as follows ;
To received
The company will receive a check for the power plant construction from EGAT every Wednesday at the end of the month and will deposit into savings accounts (Thailand) within a month to get the cheque.
If the last Wednesday of the month falls on the end of it, the Company will not pick up the cheque from EGAT. Because the bank isn't clearing cheque within a month.
The Company will receive a cheque in the next month and deposit cheque into the bank within a month to received it. - no cheque intransit.
To pay
The Company will pay to supplier by transferring money from a savings account (Thailand). - no cheque intransit.
The Company's preparation of journal instead of a bank reconcile.
- Prepared by K. Jaruwan B.
- Reviewed by K. Payao R. / K. Noboru Y.
- Approved by K. Takayuki S.