Dear Khun Chat,
Attached you can find the counting to close the agreement between CNS and SU.
As you can see there are listed the delays’ damages, some expenses about the work that you did not finish such as the forworks’ dismounting and some broken concrete part to be fixed.
As per agreement, we will keep the 10% of the total amount as guarantee and SU will give it back to you after 1 year starting since the 1st of April 2015, it means the 1st of April 2016.
A new subcontractor is going to take over the PPM2 site so please take off all your materials like wire meshes, rebar, equipment, etc.
I am available for any clarification.
Best regards