K. Suramon..
EPR process should be approved this week ( 14/10/2016)
the PO processing will be done before 19/10/2016
The draft plan for installation will be Dec 29 -31, & Jan 1, ( total 4 days).
Pls. confirm the date to me at that day IQF will be stopped , If you agreed for the plan ,
I’m afraid if any process delayed , the installation date will be delayed also .