Dear all,
Refer to our meeting this morning that we have a plan to close floor to repaint the whole corridor which will be starting during Ramadan Period. The plan will be between June 6th, to June 23rd, 2016 from the 2nd floor to 7th floor as the following detail
- 2nd floor June 06th to 08th
- 3rd floor June 09th to 11th
- 4th floor June 12th to 14th
- 5th floor June 15th to 17th
- 6th floor June 18th to 20th
- 7th floor June 20th to 23rd
Into the Guest Line System, I already put the status “out of order : maintenance” for deducting from the room availability.
Thank you for your good co-operating. Should be there quires or any assistance, please do not hesitate to contact me directly.
Best regards,
Kosol Rattanaruang
Front Office Manager