1. Purpose
The procedure stated in this document covers the activities for the installation of electrical panels such as Low Voltage & Medium Voltage Switchgears, MCC, Distribution Boards, Local Control Panel, DCS Panel & Control & Protection Panel. The constructor shall install the panels as specified herein and as detailed on the manufacturing drawing.
The requirements for the ABPR4&5 CCCP Project are in General Specification for electrical installation. If there is any discrepancy between this procedure and General Specification, the General Specification shall take the precedence.