If the Final Acceptance is not met as set forth in the time schedule, Annex II, due to reasons attributable to DÜRR, and Force Majeure is not involved, then Purchaser shall have the right to apply liquidated damages of Zero per Five cent (0.5%) of the total Contract value for every week of delay ( 7 days per week ). The grace period shall be 6 weeks. However the liquidated damages shall not exceed 5% of the total Contract value. In such case, the Purchaser shall have the right to deduct said liquidated damages from the payment under Article 5.