Following points must be pay attention by Panel Plus.
1. The wood logs are too thin and creates unnecessary down time. These need to sort and pay attention reject stations.
2. The debarking drum runs with low capacity, should run higher capacity get better debarking result. The operators have the possibility to close drum gate till they get better debarking result.
3. Press need to calibrate frequently get the optimum thickness of the boards. By last calibration the distance difference was -2.6 to 0.8mm.
4. The water tanks of press oil vapour exhaust system need to optimize. The level of water too high, particularly the water level in fibber and fume extraction tank need to reduce. The upper edge of extraction bars minimum 25% above the water that the extract the fibber/ oil mud.
5. Strongly recommended to give the instruction to operators not to ignore the warnings/ alarms in machine and if any warning/ alarm then please inform responsible person on duty.
6. Burner chamber must be controlled frequently everyday through the inspection windows. By inspection the flames must be controlled, such as flame of dust burner and the flame of grate.
7. The dust burner must be inspecting once a week by opening inspection window. Before inspecting the dust burner the must be switched off to avoid the mishap.
8. Once a month the dust burner must open for inspection if any incrustation in the burner then the burner must clean with proper cleaning equipment well.
9. The energy plant area surrounded with fibber and this could be very dangerous. Particularly the fuel transport conveyer is uncovered and this is polluting the whole area. Here is strongly recommended to put the fix back the transport cover back to avoid any kind of mishap.
10. Give the strict instruction to operators/ technicians not change the positions of sensors, limit switches and valves and manual flaps. These devices are for the human safety and as well as for safety of the machine. By replacing these devices must be fix back same position as before.
11. Operators must instructed that not change the set value rapidly and give the time to machine react on set value and watch result before change again. What I found the refiner discharge screw speed being change rapidly. Which impact on drier and on energy plant and the results are moisture fluctuation, temperature fluctuation, flow gas pressure fluctuation, fluctuation glue system and in last bad quality of product in worse case down time.
12. The biggest deficit I found in control room that there is no communication between the operators. All auf them concentrating there display but do not exchange words with each other so long machine not stop or something else not happen. The operator must have to communicate with each others when they make change in running process, hey I am going to change this and that please pay attention.
Following points must be pay attention by Panel Plus.
1. The wood logs are too thin and creates unnecessary down time. These need to sort and pay attention reject stations.
2. The debarking drum runs with low capacity, should run higher capacity get better debarking result. The operators have the possibility to close drum gate till they get better debarking result.
3. Press need to calibrate frequently get the optimum thickness of the boards. By last calibration the distance difference was -2.6 to 0.8mm.
4. The water tanks of press oil vapour exhaust system need to optimize. The level of water too high, particularly the water level in fibber and fume extraction tank need to reduce. The upper edge of extraction bars minimum 25% above the water that the extract the fibber/ oil mud.
5. Strongly recommended to give the instruction to operators not to ignore the warnings/ alarms in machine and if any warning/ alarm then please inform responsible person on duty.
6. Burner chamber must be controlled frequently everyday through the inspection windows. By inspection the flames must be controlled, such as flame of dust burner and the flame of grate.
7. The dust burner must be inspecting once a week by opening inspection window. Before inspecting the dust burner the must be switched off to avoid the mishap.
8. Once a month the dust burner must open for inspection if any incrustation in the burner then the burner must clean with proper cleaning equipment well.
9. The energy plant area surrounded with fibber and this could be very dangerous. Particularly the fuel transport conveyer is uncovered and this is polluting the whole area. Here is strongly recommended to put the fix back the transport cover back to avoid any kind of mishap.
10. Give the strict instruction to operators/ technicians not change the positions of sensors, limit switches and valves and manual flaps. These devices are for the human safety and as well as for safety of the machine. By replacing these devices must be fix back same position as before.
11. Operators must instructed that not change the set value rapidly and give the time to machine react on set value and watch result before change again. What I found the refiner discharge screw speed being change rapidly. Which impact on drier and on energy plant and the results are moisture fluctuation, temperature fluctuation, flow gas pressure fluctuation, fluctuation glue system and in last bad quality of product in worse case down time.
12. The biggest deficit I found in control room that there is no communication between the operators. All auf them concentrating there display but do not exchange words with each other so long machine not stop or something else not happen. The operator must have to communicate with each others when they make change in running process, hey I am going to change this and that please pay attention.