Please find the new coordinates of the EP2-1, with conclusion from management team we would like to complete the work as fast as possible. So please ask our contractor to support measure and boundary areas (well location, concrete area and rig camp site) same as previously location G3.
Note: I will go there on Friday to verify the location & camp area, please standby for me na krub.