This location was more difficult even with the dry materials due to the higher primary
voltage and the saturated ground. The primary voltage at Location 2 was 14.4 kV phase
to ground and initially, the interrupting fuse was 10 amperes. The 10 ampere fuse
proved to be too small and was replaced with a 20 ampere fuse. The soil and grass tests
were not attempted because of the wet condition of the test area.