6.3.1 The Contractor shall be responsible for all Contractor’s Equipment.
6.3.2 The Contractor shall be responsible (at its own cost) for:
(a) the timely importation of the Contractor's Equipment and other things which are to be imported into the country where the Site is located as required by the Contractor and/or for the Contractor’s performance of its obligations under this Contract;
(b) clearance of all items referred to in this Clause through customs in the relevant country; and
(c) if necessary under Applicable Law, ensure that the importer of record of the Contractor’s Equipment is the Owner, in accordance with the Country’s import licensing requirements with the understanding that the Contractor will, if required under Applicable Law, re-export all such imported