The work breakdown structure (WBS) defines the hierarchy of project tasks, subtasks, and work packages. Completion of one or more work packages results in the completion of a subtask: completion of one or more subtasks results in the completion of a task; and, finally, the completion of all tasks is required to complete the project. A representation of this struc- ture is shown in Exhibit 4.2.