Please be informed planning for progress and demobilization plan for your information :
Next progress report will be issued at June 20,2015. ( Slightly longer than contract )
All the package ( 165 packages) shall be finished within this target except package
which cannot completed due to plant running schedule.
Facilities will be reduced or removed step by step as mentioned below :
Nurse will be ended at June 30. ( completely 4 months )
Container will be maintain only one. ( another is our own )
Copy MC / Tent etc. will be manage as far as necessary and handled by SRT.
Site Manning will be ended at June 30, 2015.
We will stand by for few persons like safety / one engineer.
PM / SM and VV will be visit site as per situation.
SRT will stay at site until package documents handover.
So, all packages must be completed and issued for signed before target date. VV take care.
After handover , site costing will be allocated as 18 months guarantee period cost.