Engineer's Review
4.1 General
Review by the Engineer shall not be construed as a complete check, but only that the general
method of construction and detailing is satisfactory. Review shall not relieve the Contractor
from responsibility for errors or omissions which may exist.
Except where specified otherwise but within 30 days after submission to the Engineer, the
Engineer may if necessary in his opinion modify or instruct the Contractor to modify or revise
the proposed shop drawings. If the Contractor is instructed to revise or modify he shall
resubmit revised or modified shop drawings for the Engineer's review within 7 days after
such instruction is made and the 30 day period for the Engineer’s review shall recommence.
Failure to resubmit within the 7 days shall not be considered as grounds for extension of the
Contract completion date.
4.2 Authority to Proceed
The notations "Reviewed, no exceptions noted" or "Reviewed, exceptions noted" authorise
the Contractor to proceed with fabrication, purchase or both, except for those specific revision