Tun and Tor,
Confirm what you want to order with plan for the rest of phase 2 if possible (later could be acceptable)
And also send report to HO for any transfer of rebar to help
QS and purchasing,
Order whatever they want to continue working and make summary of order for other works at Aqua such as
- club house
- extra works on phase 1
- Vadim
- phase 3
Etc.
And review with BOQ again for any missing
Then prepare again report showing quantity in BOQ, order and outstanding to order