A) Forwarding company : NNE will assign our forwarding company
B) CDP Gasket : We are willing to purchase them, another change order will be issued
C) Control system issue :
I talked with Mr,Umesh(GE mapper) during his stay at NNE for GT tuning for fuel composition change-over, that we need access code for the purpose of ;
a. adjustment of parameters if we need to adjust them after calibration of any instrument, any founding of necessity of adjustment
b. mapping if we need after major inspection, any change of fuel gas condition, any repair work which need re-mapping, etc,.
c. similar level of adjustment as above which we don't know as of now
Mr Allan(GE singapore) requested NNE to talk with Mr Umesh for GE to know what NNE exactly want to get about access code.
And we are waiting for GE's answer.
We will contact GE again if they don't answer, including your comment regarding customer's right on this matter.
As for following the results of the meeting on 17 Jan.
A) Please find the attached "Off-line water washing procedure" which is prepared by our O&M company, it is prepared based on GE manual.
Please review it and feed back to us to finalize it.
B) We asked GE to confirm whether it is O.K to postpone 4000 inspection on 1~2 of June 2014, the Fired hours for GT #1 & GT #2 will be 4,300~4,500.
This is to avoid any warranty issue, We are waiting for the answer from GE
The others will be replied soon.