Dear Gidel,
Please update status in each topics as following;
Separate BU
1. When your tentative plan to complete all main Function Testing ? we will start re-testing after your confirm
GF = > tentative to test all functions by Friday, here is the current status:
Style Entry : Pass
PO : Pass
Receipt : Pass
RTV : Pass
Transfer : Pass
Adjustment : Pass
Kit Pack/Unpack : Pass
Voucher entry : Pass
SAP outbound : Pass
Replenishment : In progress
2. Replenishment issues that K.Joy sent, only type Warehouse to Store, after your fix the PO creation error, please verify Replenishment Vendor to Warehouse & store also
GF = > Replenishment Testing (Warehouse to store, Vendor to Warehouse & store) : in progress ETA by Friday
3. Please kindly shared us all issues/Status/Solution that found during verify system testing, for our team awareness during testing
GF = > All issues were related to the missing BU level price in BU2 which was fixed by Regent
Stock Ledger Entry
1. Please help to confirm Stock Ledger Entry screen can many users parallel update
GF = > Yes, this can be done in parallel as long as you don’t enter the same entry twice
2. Our Business plan to do adjust Stock Ledger & Recipe Go Live & Create New style by this end of Month(1Jul15)
Mapping New Reason Type / GL
1. Please kindly inform estimate time line to have New Reason Type mapping to new GL on VMS
From a previous email:
GF = > the effort has been estimated to 10 days and will include:
o Creating new entry types in stock ledger
o Modifying the interface jobs based on the reason codes
o Modifying period end closing
o Testing
Important Note: this mod will not work if you want to implement daily stock ledger
Dear Gidel,Please update status in each topics as following;Separate BU1. When your tentative plan to complete all main Function Testing ? we will start re-testing after your confirm GF = > tentative to test all functions by Friday, here is the current status: Style Entry : Pass PO : Pass Receipt : Pass RTV : Pass Transfer : Pass Adjustment : Pass Kit Pack/Unpack : Pass Voucher entry : Pass SAP outbound : Pass Replenishment : In progress2. Replenishment issues that K.Joy sent, only type Warehouse to Store, after your fix the PO creation error, please verify Replenishment Vendor to Warehouse & store alsoGF = > Replenishment Testing (Warehouse to store, Vendor to Warehouse & store) : in progress ETA by Friday3. Please kindly shared us all issues/Status/Solution that found during verify system testing, for our team awareness during testing GF = > All issues were related to the missing BU level price in BU2 which was fixed by RegentStock Ledger Entry1. Please help to confirm Stock Ledger Entry screen can many users parallel update GF = > Yes, this can be done in parallel as long as you don’t enter the same entry twice2. Our Business plan to do adjust Stock Ledger & Recipe Go Live & Create New style by this end of Month(1Jul15)Mapping New Reason Type / GL1. Please kindly inform estimate time line to have New Reason Type mapping to new GL on VMSFrom a previous email: GF = > the effort has been estimated to 10 days and will include:o Creating new entry types in stock ledgero Modifying the interface jobs based on the reason codeso Modifying period end closingo TestingImportant Note: this mod will not work if you want to implement daily stock ledger