4. The issuing department of this clearance certificate should be informed
immediately after de-energising / re-energising the equipment. However,
permission for any activity on the isolated equipment shall be granted by the
Operation-In-Charge only after Authorised Person of Electrical Operation
returns the original certifying job completion.
5. Switching off and isolation of space heater circuit shall be mandatory along
with de-energisation of a motor unless specifically requested in writing by
Electrical Maintenance to keep it ON.
6. After ensuring that spring is not in charged condition and damaged internals
of Breaker is rectified, rack in the breaker and put the local / remote switch in
remote position.