MET can install winch motor setting for jack up the gondola at lift machine room Level 19M (HS1).
Not have the progress install rail, bracket and etc.
Not have the progress of HS2 because install winch motor setting and prompt test on tomorrow.
Note : Lift HS1 have not progress because wait the safety to approve winch motor set and set up gondola on 6-9 August 2014.
And after that when approve winch motor to be start install.