Within these simulation runs, the same activities, constraints
and material are used. For each simulation run, the work step schedule
and the workload of employees was recorded and evaluated
afterwards. In this example, the shortest net working time is given
for the assignment of 20 workers, 4 concrete pumps and 4 substructure
equipments (Experiment 4).