I have pushed very hard to get an extension of time so that client can go-live on 6 December. That is a 3 week extension from 17 November.
So why are we still having lighting ordering problems? This is not acceptable.
Blue Clouds - Why does all meeting & training room lighting still need confirming? We have talked about these lights many many times and said they must be ordered 2 weeks ago. client already signed off. No excuse to have any of these lights missing on Day 1. Let's look at speeding up the lead time or finding similar equivalent.
Red clouds - Bernhard & Yox - we seem to have some serious lead-time & cost issues with some of the light fixtures in Cafeteria and Reception.
I am OK to wait for D7 lights because they are more decorative in nature, but please work with M24 to source D6 general lights for Cafeteria & Breakout that can meet the price and more importantly deadline. Same goes for the LED light at reception.
Thanapong - you need to help with checking where we are on the budget.