Dear all,
After check for site work drawings and as discussed during phone call, it was pointed out that the Final Issue IS02 of the Shop Drawings of the Lot 1 does not correspond to the members as fabricated.
I kindly ask you to issue the shop drawings IS03 revised, as they shall exactly correspond to the fabricated members (holes, masking, welded plates, etc. shall all comply with the material delivered).
As agreed the site works shall be indicated in separate drawings as already issued with transmittal 066 (now under check by TCM).
The reissue of the shop drawings is extremely urgent as the Final Issue IS02 can create a dangerous confusion for people at site. I kindly ask you to issue them within 19th August.