the toe failure of the hydraulic sand-fill embankment was believed
to be caused by wash water transporting the hydraulic
sand-fill at the top of the embankment at that stage of the construction,
seeping downwards through the embankment sand-fill
the construction was suspended for an investigation to be carried
out on the possibility of rapid build up of pore water pressure
within the embankment.