(ก) Subcontractor shall commence the Work as of the Effective Date. Subcontractor shall perform and complete its obligations pursuant to this Contract in accordance with the Project Master Schedule set forth in Exhibit 2.
(ข) if Subcontractor fails to complete the Work, in the case of any other activity, the time specified in the relevant schedule for the completion of such activity, Subcontractor may require to develop and submit a Remedial Plan and Subcontractor shall, at no additional cost to Contractor, diligently implement the Remedial Plan, including accelerating the performance of the Work by providing whatever reasonable means are necessary including, but not limited to, the provision of additional labor (including overtime) and Construction Equipment, in order to achieve Work Schedule provided that acceleration of the performance of the Work shall not be required if Subcontractor demonstrates to the reasonable satisfaction of Contractor and Owner that such acceleration of the Work is not required in order to achieve Work Schedule on or before.