As we discussed today, although the contract has a very basic clause pertaining to protection I will consider compensating OM on the works done.
Although Khun Steve may have asked you to do this you did not complete everything. As Khun Ouk has highlighted only 2400m2 was executed.
Your billing rate is 50 baht per m2. Hence a payment of 120,000 needs to be honored
Due to the fact that you did not complete the Job and that there are certain clauses pertaining to protection I have offered you 100,000 thai baht to close off this issue.
Hence the revised amount is 41.7 baht per m2.
Please issue a quote for his to prepare a PO of which we shall try to pay this before end May.
I will be on TK100 Monday and hope to see progress on the building since we have to handover the Podium S3 to S7 by end May.