1.) Action from the previous TCM
• Chemical warehouse delay to start in Q4 2015
• PTTEP SP explain that chemical warehouse is approved early Q1 but process for contracting a local contractor was not successful so project team had just tendered outsource contractor and the actual work will be started next month, expect to complete the end of 2015.