Step 1. All nipples, fittings, and devices
must be clean and free of scale
and burrs before installation. Use pipe
thread sealant sparingly on male pipe
threads only.
Step 2. The DV-5 Valve must be
trimmed in accordance with Figure
2A/2B and 4.
Step 3. Care must be taken to ensure
that check valves, strainers, globe
valves, etc. are installed with the flow
arrows in the proper direction.
Step 4. Drain tubing to the drip funnel
must be installed with smooth bends
that will not restrict flow.
Step 5. The main drain and drip funnel
drain may be interconnected provided
a check valve is located at least 12
inches (300 mm) below the drip funnel.