Work schedule
As a manager,the project Engineer, cannot easily adhere to a fixed working schedule,since he has to respond to often instantly arising problems and changing situations.however, a number of activities of essential importance for proper operation of a project should form fixed routines
Weekly routine during the season
Every morning : check on the actual water distribution over the water master sections in comparison with the planned distribution and initiate corrective actions when required
Tuesday : discuss next weeks water allocation plan with the head of the water Management Section and set the final plan.
Wednesday morning : chair a meeting with the water masters and the water management section on the actual and planned irrigation water distribution
Moreover,the Project Engineer Should actively supervise and support his operation staff by frequent (surprise) field visits, and attend meetings of water masters with their Zonemen or meetings with farmers
Inter - season routine
- supervision of the finishing of the seasonal Operation Evaluation Report.
- thorough discussion on the conclusions of this report.
- implementation of actions on possible improvements.
- supervision of the planning of the seasonal diversion requirement.
- thorough discussion of this planning with the dam authorities (if any).
- initiating all possible actions on further improvement on the operation of the project,especially regarding the active and effective participation of farmers and the implementation of agreed rules and regulations