If the Contractor leaves particular items unpriced it
will be deemed that the Contractor has included all
associated costs elsewhere in the Contract Bills or
that no costs will be incurred in relation to those
items, meaning that the Contractor has allowed
here for all costs, in reduction or addition, where
the Contractor has the reason to believe that the
Bill of Quantities is incorrect, making the
Contract Sum a Lumpsum amount