All work in the gym. Progress as follows
1. Remedy Room wall & ceiling at sport hall upstairs. Completed
2. Paint the PE door same color with bathroom door.Completed
3. Paint the bench in the locker room men and women.Completed
4. Renovate the office sport hall upstairs (floor,Room wall) Completed .
Just only the floor in office sport hall upstairs waiting for housekeeping try to clear if can't not clear will fix them.