If the Client suffers damage as a result of a default by the Contractor in the execution of its obligations under the Contract, the Client shall discuss the solution with the Consultant, give a written notice to the Contractor and send its copy immediately to JICA. Then the Client and the Contractor shall consult mutually to settle such matters. The Client shall properly inform JICA of its progress. If the Parties cannot reach agreement within thirty (30) days from the date of the notice, the Parties shall comply with the dispute settlement process stipulated in Article 18 hereof.