As K.Chartchai inform this morning, UTCT want to finish select contractor in Jan 16 and want to start project Feb 16. Then the consulting, we need to hire in Jan 16 also for take care selection, material will use and supervision. Please find quotation of consultant fee in attached file.
Tentative repair schedule below was recommended :-
1. Finalize the repair cost comparison and select vendor not later than end January , 16.
2. Commence wharf repair by February , 16.