• As a rough estimate it is useful to think in terms of a one third split between conceptual modelling (including data collection and analysis), model coding and experimentation, bearing in mind that each of these processes is regularly revisited during the life of a project.
• In stating this, the need for verification and validation is included as part of the time devoted to each process.
• Model coding, therefore, may be as little as 20% of the total time required for the simulation project.Simulation Project