Level No. 1 Consists of a Pre-Inspection Meeting to establish hold points and weekly or bi-weekly in-process surveillance visits. When required by the Project and Manager of Inspection this level could consist of resident inspection.
Level No. 2 Consists of a Pre-Inspection Meeting to establish hold points and the specified in-process surveillance visits designated in the Inspection and Test Plan. In-process visits can be weekly or biweekly as designated by project.
Level No. 3 Consists of in-process visits as designated by the Inspection and Test Plan followed by Final Inspection or Final Inspection only at the Supplier’s facility.
Level No. 4 Consists of a Final Inspection upon arrival at the jobsite. No visit to the Supplier’s facility will be made.