The contingency account should be regularly assessed as to the contingency required for the remaining
work. This is done using the methods of the risk management process (Section 7.6). That process evaluates
and quantifies the impact of any risk factors inherent to the revised scope and plans. After a corrective
action is decided upon, the risk management plan is updated.